Total Capital Investment (TCI) Breakdown: Fixed Capital vs Working Capital
Calculates the detailed sub-elements of Total Capital Investment (TCI), establishing Working Capital components, prepaid royalties, catalyst initial charges, and land acquisition costs.
1. Theoretical Foundations & Engineering Mechanics
Detailed Capital Investment Breakdown
Total Capital Investment ($TCI$) is the total funds that an operating corporation or equity syndicate must finance to design, procure, construct, commission, and successfully initiate commercial production of a chemical facility.
1. Inside vs Outside Battery Limits (ISBL vs OSBL)
• ISBL (Inside Battery Limits): The core process boundary encompassing reactors, distillation trains, heat exchangers, pumps, piping, instrumentation, and control rooms.
• OSBL (Outside Battery Limits): Offsite auxiliary facilities required to support the process unit:
- Steam boilers, cooling towers, demineralized water plant, compressed air
- Raw material bulk storage tanks and finished product tank farms
- Flare systems, wastewater treatment plants (WWTP), electrical substations, firewater systems
- Rail loading racks, truck bays, administrative offices, and QA/QC analytical laboratories.
2. Working Capital Formulation
Working capital represents the non-depreciable revolving capital invested to bridge the operational time lag between purchasing raw materials and collecting cash receipts from finished product sales:
$$WC = \text{Raw Materials Inventory} + \text{In-Process Inventory} + \text{Finished Product Inventory} + \text{Accounts Receivable} - \text{Accounts Payable}$$
In early project phases, working capital is reliably estimated as $15\%$ to $20\%$ of Fixed Capital Investment ($FCI$) or $15\%$ of annual sales revenue. Crucially, unlike fixed plant assets, working capital is fully recoverable at the end of the project life cycle.
2. Governing Equations & Mathematical Formulation
$$TCI = FCI_{\text{direct}} + FCI_{\text{indirect}} + WC + C_{\text{land}} + C_{\text{catalyst, initial}}$$
$$FCI_{\text{direct}} = ISBL + OSBL$$
$$FCI_{\text{indirect}} = EPCM + \text{Contractor Fee} + \text{Contingency}$$
$$WC = N_{\text{days}} \cdot \left(\frac{OPEX}{365}\right) + \text{Accounts Receivable} - \text{Accounts Payable}$$
• Land cost is treated as a separate non-depreciable asset.
• Initial precious-metal catalyst charge with multi-year life is capitalized under initial investment.
• Working capital is 100% recovered at salvage value at project termination.
• Treating working capital as a depreciable tax asset (tax laws forbid depreciating cash/inventory balances).
• Overlooking the immense initial catalyst charge cost in hydrocrackers or reforming units ($10M to $30M for platinum/palladium).
• Underestimating offsite utility supply capacity when connecting to existing utility headers.
3. Applied Engineering Worked Example
A prospective chemical plant budget specifies:
• Direct Installed ISBL equipment cost = $80.0 million USD
• Direct OSBL offsites and utilities = $32.0 million USD
• Indirect costs (engineering, legal, contractor fee) = $22.4 million USD
• Project contingency = $13.44 million USD
• Non-depreciable land acquisition = $5.0 million USD
• Initial noble metal catalyst charge = $8.0 million USD
Working capital is set at 18% of Fixed Capital Investment ($FCI$).
Calculate:
1. The Total Fixed Capital Investment ($FCI$) in millions of USD.
2. The Working Capital ($WC$) in millions of USD.
3. The Total Capital Investment ($TCI$) in millions of USD.
Step 1: Total Fixed Capital Investment (FCI)
$$FCI = \text{ISBL} + \text{OSBL} + \text{Indirects} + \text{Contingency}$$
$$FCI = 80.0 + 32.0 + 22.4 + 13.44 = \$147.84\text{ million USD}$$
Step 2: Working Capital (WC)
$$WC = 0.18 \times FCI = 0.18 \times 147.84 = \$26.611\text{ million USD}$$
Step 3: Total Capital Investment (TCI)
$$TCI = FCI + WC + C_{\text{land}} + C_{\text{catalyst}}$$
$$TCI = 147.84 + 26.611 + 5.0 + 8.0 = \$187.451\text{ million USD}$$
Final Answer:
FCI = $147.84M USD; Working Capital = $26.61M USD; Total Capital Investment (TCI) = $187.45M USD.