Learn / Process Equipment Design & Economics / Capital & Operating Cost Estimation
Capital & Operating Cost Estimation 0 Practice Questions

Equipment Factored Sizing (Hand Factors, Chilton Method)

Evaluates intermediate factored cost estimation methodologies (AACE Class 4), applying Hand factors (individual equipment multipliers) and Chilton sub-factors for piping, civil, and electrical.

Practice Questions ↓

1. Theoretical Foundations & Engineering Mechanics

Factored Cost Estimation: Hand and Chilton Methods

In preliminary process design and feasibility studies (AACE International Class 4 estimates, accuracy $-15\%$ to $+30\%$), sizing every individual pipe, foundation, cable tray, and instrument loop is impractical. Instead, engineers employ factored cost estimation techniques that correlate the total installed battery-limits cost (ISBL) directly to the purchased cost of major process equipment ($C_E$).

While the classical Lang factor applies a single monolithic multiplier to total equipment cost ($f_{\text{Lang}} = 4.74$ for fluids, $3.63$ for solids-fluids), it fails to account for varying equipment mixes. A plant dominated by expensive compressors has a much lower piping ratio than one dominated by distillation columns.

1. Hand's Factored Cost Methodology (1958)

W. E. Hand refined capital costing by assigning individual installation factors ($f_{\text{Hand}, i}$) specific to each equipment class. The total fixed capital investment is the sum of each delivered equipment cost multiplied by its distinct factor:
$$C_{\text{ISBL}} = \sum_{i=1}^M f_{\text{Hand}, i} C_{E, i}$$

Standard Hand factors for carbon steel equipment installed on site include:
- Fractionation Columns / Distillation Towers: $f_{\text{Hand}} = 4.0$ (reflects extensive internal trays, reflux piping, and high-altitude structural platforms).
- Pressure Vessels and Accumulators: $f_{\text{Hand}} = 4.0$.
- Shell & Tube Heat Exchangers: $f_{\text{Hand}} = 3.5$ (requires piping, insulation, foundation, and bypass valves).
- Centrifugal Pumps and Drivers: $f_{\text{Hand}} = 4.0$ (dual piping, check valves, suction strainers, foundation pad, and electrical switchgear).
- Centrifugal Compressors and Fired Heaters: $f_{\text{Hand}} = 2.5$ to $3.0$ (the high base purchase price of rotating machines already embodies significant shop fabrication, reducing the installation ratio).
- Atmospheric Storage Tanks: $f_{\text{Hand}} = 2.0$ to $2.5$.

2. Chilton's Itemized Direct and Indirect Factor Breakdown

C. H. Chilton (1949) decomposed fixed capital investment into itemized module percentages relative to delivered equipment cost ($C_E$):
- Direct Costs:
- Purchased Equipment ($C_E$): $1.00$
- Equipment Installation: $0.35 - 0.45 C_E$
- Process Piping (installed): $0.30 - 0.70 C_E$ (higher for corrosive/high-pressure fluids)
- Instrumentation & Controls: $0.15 - 0.35 C_E$ (higher for distributed DCS/SIS)
- Electrical Systems: $0.10 - 0.20 C_E$
- Civil, Buildings & Structures: $0.15 - 0.30 C_E$
- Yard Improvements & Fire Protection: $0.05 - 0.15 C_E$
- Indirect Costs:
- Engineering, Procurement & Construction Management (EPCM): $0.20 - 0.35 C_E$
- Construction Expenses & Field Supervision: $0.10 - 0.20 C_E$
- Contractor Fee & Legal: $0.05 - 0.10 C_E$
- Contingency (AACE Class 4): $0.15 - 0.25 (\text{Direct} + \text{Indirect})$

2. Governing Equations & Mathematical Formulation

$$C_{\text{ISBL}} = \sum_{i=1}^M f_{\text{Hand}, i} C_{E, i}$$
$$C_{\text{FCI}} = \sum C_{\text{direct}} + \sum C_{\text{indirect}} + C_{\text{contingency}}$$
$$\text{Lang Factor Limit: } C_{\text{FCI}} = f_{\text{Lang}} \sum C_{E, i}$$
$$f_{\text{composite}} = \frac{\sum f_{\text{Hand}, i} C_{E, i}}{\sum C_{E, i}}$$

💡 Formulated according to international process engineering standards and dimensionless groups.
📌 Key Engineering Assumptions

• Major equipment costs are based on delivered carbon steel purchase prices at current base year.
• Plant battery limits (ISBL) are located on normal soil conditions without deep pilings or rock excavation.
• Alloy equipment requires alloy piping adjustment (Hand factors assume carbon steel bases).
• Utility supply is available at the battery limits without massive greenfield offsites expansions.

⚠️ Common Industrial Pitfalls

• Applying carbon steel Hand factors directly to exotic alloy equipment (Hastelloy, Titanium); since base equipment is 4x more expensive, piping does not scale 4x, artificially inflating the estimate.
• Double-counting contractor fees or contingency when using all-inclusive Hand factors.
• Neglecting offsites (OSBL) infrastructure (cooling towers, flare system, substation) which adds 20% to 40% to ISBL.

3. Applied Engineering Worked Example

Design Problem Specification

A grassroots chemical processing unit has the following delivered carbon steel equipment costs: Distillation Column (C_E1 = $320,000), Heat Exchangers (3 units, total C_E2 = $240,000), Centrifugal Pumps with motors (4 units, total C_E3 = $85,000), and Centrifugal Gas Compressor (C_E4 = $650,000). Hand factors are: Towers = 4.0, Exchangers = 3.5, Pumps = 4.0, Compressor = 2.5. Offsites (OSBL) and contingency add 30% to ISBL.

Step-by-Step Mathematical Derivation & Verification

Step 1: Calculate Total Purchased Equipment Cost (C_E)
$$C_E = \$320,000 + \$240,000 + \$85,000 + \$650,000 = \$1,295,000$$

Step 2: Apply Hand Factors to Each Equipment Category
- Distillation Tower: $\$320,000 \times 4.0 = \$1,280,000$
- Heat Exchangers: $\$240,000 \times 3.5 = \$840,000$
- Pumps & Drivers: $\$85,000 \times 4.0 = \$340,000$
- Centrifugal Compressor: $\$650,000 \times 2.5 = \$1,625,000$

Step 3: Calculate Installed Battery-Limits Cost (C_ISBL)
$$C_{\text{ISBL}} = \$1,280,000 + \$840,000 + \$340,000 + \$1,625,000 = \mathbf{\$4,085,000}$$

Step 4: Determine Composite Hand Factor
$$f_{\text{composite}} = \frac{C_{\text{ISBL}}}{C_E} = \frac{\$4,085,000}{\$1,295,000} = \mathbf{3.155}$$
Notice that due to the heavy compressor contribution, the composite factor (3.15) is significantly lower than the standard fluid Lang factor (4.74), preventing a $2 million over-estimation.

Step 5: Add Offsites and Contingency (30%)
$$C_{\text{FCI}} = C_{\text{ISBL}} \times 1.30 = \$4,085,000 \times 1.30 = \mathbf{\$5,310,500}$$

Interactive Practice Drill: Equipment Factored Sizing (Hand Factors, Chilton Method)

Instant answer checking, step rationales, and tolerance scoring.
Question 1 of 15
Loading interactive questions...

Completed this lesson?

Record your study progress, build your daily streak, and unlock +25 XP toward your next engineering tier.