Learn / Process Safety & Loss Prevention / Process Safety Management (PSM) & Toxicology
Process Safety Management (PSM) & Toxicology 36 Practice Questions

Process Safety Information (PSI), MOC (Management of Change) & PSSR Procedures

Implements core operational process safety workflows, establishing technical specifications for Process Safety Information (PSI), Management of Change (MOC) multi-discipline reviews, and Pre-Startup Safety Reviews (PSSR).

Practice Questions ↓

1. Theoretical Foundations & Engineering Mechanics

Process Safety Information (PSI), MOC, and PSSR

Process Safety Information (PSI), Management of Change (MOC), and Pre-Startup Safety Reviews (PSSR) form the operational core of OSHA PSM and EPA Risk Management Program (RMP) regulations.

1. Process Safety Information (PSI, 1910.119d)

PSI provides the complete technical baseline required to execute meaningful PHAs and design relief systems. PSI spans three domains:
1. Hazards of the Chemicals: Toxicity, permissible exposure limits (PEL), physical constants, reactivity, thermal instability, corrosive effects.
2. Technology of the Process: Block flow diagrams (BFD), simplified process flow diagrams (PFD), maximum intended inventories, safe upper/lower operating limits (temperature, pressure, flow), and chemical reaction kinetics.
3. Equipment Design Codes: Materials of construction, P&IDs, electrical classification, relief valve design basis, ventilation design, and safety interlock cause-and-effect matrices.

2. Management of Change (MOC, 1910.119l)

Any change in process chemicals, technology, equipment, operating procedures, or staffing—except for "replacement in kind" (RIK)—must undergo a formal MOC process:
• Technical basis and justification for the proposed change
• Impact of change on process safety, occupational health, and environmental emissions
• Modifications to operating and maintenance procedures
• Necessary authorization signatures from engineering, operations, and process safety.

3. Pre-Startup Safety Review (PSSR, 1910.119i)

Before hazardous chemicals are introduced into a new or modified facility, a multidisciplinary PSSR team conducts physical on-site field verification: construction matches design specs, safety devices are calibrated, procedures are updated, and operating training is complete.

2. Governing Equations & Mathematical Formulation

$$\text{MOC Workflow: } \text{Initiate} \rightarrow \text{Technical Review} \rightarrow \text{PHA/Risk} \rightarrow \text{Approval} \rightarrow \text{Execute} \rightarrow \text{PSSR} \rightarrow \text{Closeout}$$
$$\text{RIK Test: } \text{Spec}_{\text{new}} \equiv \text{Spec}_{\text{original}} \implies \text{RIK (No MOC Required)}$$
$$\text{Temporary MOC: } t_{\text{active}} \le t_{\text{authorized limit}} \quad (\text{typically } \le 6 \text{ months})$$

💡 Formulated according to international process engineering standards and dimensionless groups.
📌 Key Engineering Assumptions

• RAGAGEP (Recognized and Generally Accepted Good Engineering Practices) standards govern all PSI design baselines.
• All PSSR "Category A" punch-list action items must be closed before introducing process fluids.
• Temporary MOCs automatically expire unless formally extended through renewed technical review.

⚠️ Common Industrial Pitfalls

• Allowing temporary modifications (e.g. bypassing an interlock or installing a temporary jumper hose) to persist indefinitely without an MOC.
• Signing off on PSSRs from behind a desk without physically walking the piping system in the field.
• Maintaining out-of-date P&IDs that fail to reflect past MOC modifications.

3. Applied Engineering Worked Example

Design Problem Specification

A plant engineering team plans to replace a failing control valve on a high-pressure reactor feed line. Original valve: 2-inch ANSI 300 globe valve, equal percentage trim, $C_v = 45$, Stellite hard-facing. Proposed replacement: 2-inch ANSI 300 globe valve from an alternate vendor, linear trim, $C_v = 60$, 316SS trim.
1. Evaluate whether this modification qualifies as a "Replacement-in-Kind" (RIK).
2. Identify the required safety workflow elements that must be executed before commissioning.

Step-by-Step Mathematical Derivation & Verification

Step 1: Evaluate Replacement-in-Kind (RIK) Status
An RIK requires identical physical, metallurgical, and functional performance specifications. Here:
• The trim characteristic is modified from equal-percentage to linear.
• The flow capacity $C_v$ is increased from 45 to 60 ($+33.3\%$ flow capacity).
• The trim material is downgraded from erosion-resistant Stellite to 316 stainless steel.
The higher $C_v$ increases maximum emergency relief overfeed rates, and the linear trim alters loop dynamics. Therefore, this change is NOT a Replacement-in-Kind.

Step 2: Required Safety Workflow Elements
1. MOC Initiation: Document technical basis and safety impact of the higher $C_v$ on downstream reactor runaway risk.
2. Relief Review: Re-evaluate downstream relief valve sizing for the higher maximum flow capacity ($C_v = 60$).
3. PSI Update: Update instrument datasheets, valve index, and loop tuning files.
4. PSSR: Conduct physical pre-startup field inspection before opening isolation block valves.

Final Answer:
NOT a Replacement-in-Kind (Cv changed 45 -> 60, trim altered); Mandatory MOC, relief re-rating, PSI update, and PSSR required.

Interactive Practice Drill: Process Safety Information (PSI), MOC (Management of Change) & PSSR Procedures

Instant answer checking, step rationales, and tolerance scoring.
Question 1 of 15
Loading interactive questions...

Completed this lesson?

Record your study progress, build your daily streak, and unlock +25 XP toward your next engineering tier.