Hazard Identification (HAZID) & Human Factors Engineering in Hazard Reviews
Integrates high-level Hazard Identification (HAZID) and Human Factors Engineering (HFE) into capital project design, analyzing ergonomics, alarm flood management (EEMUA 191), and human error probabilities.
1. Theoretical Foundations & Engineering Mechanics
HAZID and Human Factors Engineering (HFE)
Major process plant disasters (e.g. Three Mile Island, Texas City, Macondo) demonstrate that safety failures rarely stem solely from isolated hardware breakdowns; they frequently result from Human Factors Engineering (HFE) deficiencies where control systems overwhelm human cognitive capabilities during plant upsets.
1. The HAZID Study (Early Project Gate)
Conducted during conceptual / FEED phases, HAZID screens macroscopic project site risks before detailed P&IDs exist:
• Natural hazards (earthquakes, storm surges, flooding, lightning strikes)
• External logistics (ship collisions, neighboring facility fires, aircraft flight paths)
• Plot plan layout (separation distances between tank farm, control room, and process units).
2. Human Factors: Alarm Management (EEMUA 191 / ISA-18.2)
During a plant upset, a phenomenon termed alarm flooding occurs when an operator receives dozens of alarms per minute, inducing panic, cognitive overload, and missed critical trip signals. EEMUA Publication 191 and ISA-18.2 establish strict industry benchmarks:
| Operational State | Acceptable Alarm Rate | Average Interval between Alarms |
|---|---|---|
| Normal Steady-State | $< 1$ alarm per 10 minutes | $> 10$ minutes |
| Manageable Upset | $< 2$ alarms per 10 minutes | $> 5$ minutes |
| Major Plant Upset (First 10 min) | $< 10$ alarms per 10 minutes | $\ge 1$ minute |
Rationalization techniques (alarm deadbands, dynamic alarm suppression, state-based alarming) eliminate nuisance chattering alarms.
3. Human Error Probability (THERP and HEART Models)
Human Error Probability ($HEP$) for routine tasks under low stress is $10^{-3}$ ($1$ error per $1,000$ operations), but escalates to $0.25 - 0.50$ under severe emergency time pressure without automated interlocks.
2. Governing Equations & Mathematical Formulation
$$\text{Alarm Rate} \le 1 \text{ alarm / 10 minutes (Normal)}$$
$$HEP = HEP_0 \times \prod \text{PSF}_i \quad (\text{Performance Shaping Factors})$$
$$\text{Safe Separation: } D_{\text{plot}} \ge f(\text{Blast/Radiation Contour})$$
• Control room operators have completed simulator and console qualification training.
• Alarm priority distribution conforms to ISA-18.2 (Low 80%, Medium 15%, High 5%).
• Critical manual operator actions allow at least 15 to 20 minutes before irreversible consequence occurs.
• Alarm standing: operating with dozens of acknowledged active alarms permanently illuminated on screens.
• Designing safety-critical manual valves in inaccessible pipe rack elevations without permanent chain wheels or platforms.
• Relying on operator memory during stressful emergency trips without simple paper or DCS-guided checklists.
3. Applied Engineering Worked Example
During a boiler trip upset at a chemical plant, the central DCS console generates 240 alarms within the first 10 minutes. Per ISA-18.2 / EEMUA 191 standards, the maximum acceptable alarm rate during the first 10 minutes of an upset is 10 alarms per 10 minutes (1 alarm/minute).
Calculate:
1. The average alarm presentation rate experienced by the board operator in alarms per minute.
2. The ratio by which the actual alarm flood exceeds the maximum acceptable industry benchmark.
3. State two specific engineering techniques to eliminate this alarm flood.
Step 1: Calculate Actual Alarm Rate
$$\text{Actual Rate} = \frac{240\text{ alarms}}{10\text{ minutes}} = 24.0\text{ alarms/minute}$$
The operator receives an alarm every $2.5\text{ seconds}$, making diagnosis cognitively impossible.
Step 2: Compare with Industry Benchmark
Benchmark target: maximum $1.0\text{ alarm/minute}$ ($10\text{ alarms in 10 minutes}$).
$$\text{Exceedance Ratio} = \frac{24.0}{1.0} = 24.0$$
The alarm presentation rate exceeds the acceptable human cognitive handling limit by a factor of 24x (a severe alarm flood).
Step 3: Engineering Solutions for Alarm Flood Elimination
1. State-Based / First-Out Dynamic Alarm Suppression: Configure DCS logic so that when the main boiler master fuel trip occurs, all secondary consequential cascading alarms (low steam pressure, low burner header pressure, flame out on 12 burners) are automatically suppressed, presenting only the single "first-out" root-cause alarm.
2. Alarm Rationalization: Implement deadbands and delay timers to eliminate chattering and duplicate instrument alarms.
Final Answer:
Alarm rate = 24 alarms/min; Exceeds ISA-18.2 benchmark by 24x (severe flood); Solution: State-based suppression & alarm rationalization.