Discounted Cash Flow (DCF) & Time Value of Money
Establishes the time value of money, compound interest formulas, discrete vs continuous compounding, and the construction of multi-year Discounted Cash Flow (DCF) project schedules.
1. Theoretical Foundations & Engineering Mechanics
Time Value of Money and Discounted Cash Flow (DCF)
A dollar received today is worth more than a dollar received five years from today because capital today can earn productive compound interest and avoid purchasing power erosion from inflation. In chemical engineering capital project evaluation, all future cash inflows and outflows must be discounted back to the Present Value (PV) at the corporate hurdle discount rate $i$ (or Weighted Average Cost of Capital, WACC).
1. Compound Interest and Discount Factors
For an interest rate $i$ compounded annually over $n$ years, future value $F$ and present value $P$ are related by:
$$F = P (1 + i)^n \implies P = \frac{F}{(1 + i)^n} = F \cdot DF_n$$
where $DF_n = (1 + i)^{-n}$ is the discount factor for year $n$.
For continuous compounding at nominal annual rate $r$:
$$F = P e^{r n} \implies P = F e^{-r n}$$
2. Annuities and Uniform Series
A uniform annual series of cash flows $A$ over $n$ years has a present worth given by the Uniform Series Present Worth factor ($P/A, i, n$):
$$P = A \left[ \frac{(1 + i)^n - 1}{i (1 + i)^n} \right]$$
3. DCF Schedule Structure
A multi-year discounted cash flow model maps each project period $t$:
1. Capital investment outflows in construction years ($t = -2, -1, 0$)
2. Sales revenues minus variable and fixed OPEX ($t = 1 \dots N$)
3. Tax deductions for depreciation and corporate income tax payments
4. Working capital recovery and salvage value in terminal year $N$.
2. Governing Equations & Mathematical Formulation
$$PV = \sum_{t=0}^{N} \frac{CF_t}{(1 + i)^t}$$
$$DF_t = (1 + i)^{-t}$$
$$P = A \left[ \frac{(1 + i)^n - 1}{i (1 + i)^n} \right] = A (P/A, i, n)$$
$$A = P \left[ \frac{i (1 + i)^n}{(1 + i)^n - 1} \right] = P (A/P, i, n)$$
• Cash flows are assumed to occur as lump sums at year-end (discrete discounting convention).
• The discount rate $i$ remains constant over the full economic life of the project.
• Reinvestment of positive intermediate cash flows occurs at the project discount rate $i$.
• Mixing nominal cash flows (inflated dollars) with real discount rates (inflation-free), distorting PV.
• Treating multi-year EPC construction spending as an instantaneous outflow at $t=0$.
• Forgetting the inverse relationship between interest rates and present value; higher interest rates penalize long-payback capital projects severely.
3. Applied Engineering Worked Example
An energy-efficiency revamp of an industrial furnace costs $P = \$1,200,000\text{ USD}$ installed at $t = 0$. The revamp generates fuel savings of $A = \$320,000\text{ USD/year}$ for the next 5 years (Years 1 through 5). The company's hurdle discount rate is $i = 10.0\%$.
Calculate:
1. The discount factors for Years 1 through 5.
2. The cumulative Present Value ($PV$) of the fuel savings using the uniform series factor.
3. The Net Present Value ($NPV$) of the revamp project.
Step 1: Calculate Uniform Series Present Worth Factor
$$i = 0.10, \quad n = 5$$
$$(1 + i)^n = (1.10)^5 = 1.61051$$
$$(P/A, 10\%, 5) = \frac{1.61051 - 1}{0.10 \times 1.61051} = \frac{0.61051}{0.161051} = 3.79079$$
Step 2: Present Value of Annual Savings
$$PV = A \times (P/A, 10\%, 5) = \$320,000 \times 3.79079 = \$1,213,053\text{ USD}$$
Step 3: Net Present Value (NPV)
$$NPV = PV - P_0 = \$1,213,053 - \$1,200,000 = +\$13,053\text{ USD}$$
Since $NPV > 0$, the project exceeds the 10% corporate hurdle rate and is economically justified.
Final Answer:
Uniform series factor = 3.791; PV of savings = $1,213,053; Project NPV = +$13,053 USD.