๐Ÿ“ DATASHEET AUDIT TAG: C-301 ๐Ÿ“œ Fractionation Research Inc. (FRI) / Glitsch Guidelines

Fractionator Column Tray Hydraulics Audit (C-301 Valve Trays)

Interactive Industrial Simulation โ€ข Standards Verification โ€ข Reward: +175 XP

Reward
+175 XP
๐Ÿ“

Interactive Process & Instrumentation Schematic

ISA-5.1 Vector Standard
Downcomer Backup = 78.2%! Polymer Grade Propylene Vapor ! C-301 Splitter
๐Ÿ’ก Inspect nozzle configurations, flow directions, instruments, and discrepancy flags marked with !

1. Industrial Operating Briefing

Context & Boundaries

Audit the internal hydraulic rating sheet for C-301, a superfractionator column separating propylene from propane with 180 high-efficiency movable valve trays. At a high reflux ratio ($R/D = 14$), vapor-liquid traffic is intense. Audit the downcomer backup percentage, jet flood percentage, weir crest height, and tray spacing.

2. Equipment Process Datasheet

Specifications Under Review
Tray Type Moving Valve Trays, 4-Pass Hydraulic Layout
Tray Spacing 450 mm (18 inches)
Equipment Tag C-301
Downcomer Backup % 78.2% of Tray Spacing
Reflux Ratio (L/D) 14.2
Tray Count / Service 180 Trays / C3 Splitter (Polymer Grade Propylene)
Weir Height / Length 50 mm / 3.8 m per pass
Top Section Jet Flood % 89.5% of Flood
Column Diameter (Top / Bottom) 5.4 m / 5.4 m
Operating Pressure (Top / Bottom) 17.5 barg / 21.0 barg
Liquid Flow Rate per Unit Weir Length 78 mยณ/(hยทm)
โšก Verify in ChemProCal Live Tool

Open the dedicated engineering calculator to independently verify velocities, duties, and hydraulic limits.

Open Flash Drum Sizing โ†—

3. Datasheet Audit Findings Checklist

Simulation Active

Audit the process datasheet against design standards. Check all discrepancies and design oversights you have identified: